Stellantis Future Product For U.S. Shown In UAW Agreement

New Durango Planned, Gladiator 4xe In 2025, and All-Electric Wrangler In 2027...

While the United Auto Workers (UAW) are celebrating their record tentative agreement with Stellantis, it has allowed us to see the future intentions of Stellantis (FCA US, LLC) operations in the United States until 2028. This allows us to see a timeline of future products and the plants, as well as the mid-cycle action (MCA) or “refreshes” for existing products. So, we thought we would take a deep dive into it all.

Belvidere Assembly Plant – 

Belvidere Assembly Plant. (Stellantis).

Belvidere will get a $1.5 billion investment to launch all-new midsize trucks in 2027, with an annual projection of 80,000 to 100,000 units. So yes, the production of these trucks is still a long time out. But what makes us curious is the plan for the plant states trucks as plural. So, could there be more than just one midsize truck in the lineup other than the Ram brand? We don’t know.

Detroit Assembly Complex (Mack and Jefferson) – 

Detroit Assembly Complex – Mack Facility. (Stellantis).

The facilities will split a $1.5 billion investment to continue to build the popular Jeep® Grand Cherokee and Dodge Durango vehicles. This includes their replacements. 

  • The current Dodge Durango (WD) will continue production through 2025 in its current state.
  • An all-new Dodge Durango (D6U) will start production in 2026 and offer both internal combustion engine (ICE) and battery-electric (BEV) options.
  • The current Jeep Grand Cherokee (WL74) two-row will continue through 2027, while the (WL75) three-row will continue through 2028. Both vehicles will receive a MCA in 2024 for the 2025 model year.
  • The next-generation Grand Cherokee (J6U) will include ICE and BEV variants and will launch in 2027.

Toledo Assembly Complex (North and South) – 

Toledo Assembly Complex – North. (Stellantis).

Stellantis will invest an additional $1.5 billion into its Toledo Assembly operations. The agreement states the following…

  • Both the current Wrangler (JL) and Gladiator (JT) will continue into 2028
  • MCA for Gladiator is happening now.
  • Wrangler PHEV 4xe Upgrade is scheduled for 2025, as is the new Gladiator PHEV 4xe.
  • Next-Gen Wrangler (J70) will launch in 2028, with both BEV and Range Electric Paradigm Breaker (REPB). The REPB will use an ICE as a generator instead of powering the wheels, allowing the battery to be recharged on the go, extending range according to our sources.

Warren Truck Assembly Plant – 

Warren Truck Assembly Plant. (Stellantis).

Stellantis will invest $600 million into its Warren Truck operations for current and future products. This includes…

  • The current Ram 1500 Classic (DS) will continue production through 2024.
  • The current generation of Wagoneer/Grand Wagoneer (WS) will continue production into 2028.
  • Both the Wagoneer/Grand Wagoneer are scheduled for two MCAs, the first in 2025 and the second in 2027
  • A Wagoneer/Grand Wagoneer REPB variant will start production in 2025
  • A Wagoneer/Grand Wagoneer BEV variant will start production in 2027

Sterling Heights Assembly Plant – 

Sterling Heights Assembly Plant. (Stellantis).

The automakers plan to invest an additional $1.4 billion into its most profitable plant, Sterling Heights Assembly Plant. The 5 million square foot facility is home to the Ram 1500 (DT) pickup.

  • The current Ram 1500 (DT) will continue production through the 2024 model year.
  • A MCA for the Ram 1500 will happen in 2024.
  • Sterling Heights will also produce the Ram 1500 REV BEV and REV XR REPB in 2024.

Battery Plants in the U.S. – 

Construction workers secure the first piece of steel raised into place for the Stellantis and Samsung SDI Gigafactory. (Stellantis).
 

Belvidere – Launch a new joint venture (JV) battery operation in 2028 with a yet-to-be-identified business partner. Will invest $3.2 billion into the facility, which will generate an estimated 1,300 jobs.

Kokomo – Stellantis has committed to build two new battery plants in Kokomo. It’s a $6.2 billion investment that the company estimates will create 2,600 permanent jobs. The plants are a JV with Samsung SDI.

Mopar Hubs – 

Mopar Parts Distribution Center in Romulus, Michigan. (Stellantis)

According to the agreement, Mopar will consolidate its Product Distribution Centers (PDCs) into new hubs. This means some Mopar PDCs will be closed, and operations will move to six new Hubs. The UAW says while Stellantis will complete some of the facilities, the union got the elimination of the lower wage tier at Mopar, a guarantee of job security, and the right to bargain for an expanded moving allowance beyond the $37,500 they already won.

Belvidere Consolidated Mopar Mega Hub – A new $100 million investment that will launch in 2024 through the consolidation of work from the Marysville, Chicago, and Milwaukee PDCs. Introduce Stamping operations to support replacement parts for the Belvidere Mega Hub in 2025.

Fishkill, NY Mopar Hub – A new $30 million investment launch in 2025 with the consolidation of work from the New York and Boston PDCs.

Macon, GA Mopar Hub – A new $30 million investment launch in 2026 with the consolidation of work from the Orlando and Atlanta PDCs.

Metro Detroit Region Mopar Hub – A $30 million investment launch in 2026 with the consolidation of work from the Centerline PDC, Centerline Warehouse & Packaging, Warren PDC, and Sherwood PDC.

Reno, Nevada PDC – A new $30 million investment launch is projected in 2027 with the consolidation of work from the LA PDC.

South Central TX PDC – A new $30 million investment launch is projected in 2026 with the consolidation of work from the Dallas PDC.

Powertrain Facilities – 

Kokomo Transmission Plant. (Stellantis).

Kokomo Casting – Stellantis will invest $160 million into the 625,000-square-foot facility in Indiana. This will include the following operations…

  • Continued production of various engine blocks and components, transmission cases, and components & chassis components.
  • Launch WL & LB Crossmembers in 2024.
  • Launch EDM Gearbox Cover in 2024.
  • Launch GME-T6 (HURRICANE I6) Oil Pan in 2024.
  • Launch the EP6 (New 1.6-liter) Bedplate in 2025.
  • Launch the EP6 Block in 2025.
  • Launch eMotors Housing and Cover in 2026.

Kokomo Engine – Production of the GME-T4 DOHC (turbocharged 2.0-liter I4) will continue into 2028.

Kokomo Transmission – The facility will get a $450 million investment. The product at the facility will look like this…

  • Production of the current 850RE 8-Speed Automatic will continue into 2028.
  • Launch of a new 880RE Gen4 8-Speed Automatic in 2024.
  • Current production of the single-input electrically variable transmission (Si-EVT) used in the Chrysler Pacifica Hybrid will continue into 2028.
  • Introduce Electric Drive Motor Gearbox Covers in 2024
Indiana Transmission –  The 1.2 million square foot Kokomo, Indiana facility will get a $900 million investment for the following…
 
  • Current production of the 948TE 9-Speed Automatic will continue into 2028.
  • Current production of the 68RFE 6-Speed Automatic used in Ram Heavy Duty trucks will continue into 2024.
  • Launch Phase I of Electric Drive Motor Gear Machining & Assembly in 2024.
  • Launch Phase II of Electric Drive Motor Gear Machining & Assembly in 2025.
  • Launch e-Motor Assembly in 2026.

Trenton Engine – The Trenton Engine facility will continue to produce Pentastar V6 engines.

  • Pentastar Classic continues through 2024.
  • Pentastar Upgrade continues through 2028.

Dundee Engine Plant North & South – The Dundee Engine will get an investment of $770 million and produce two new engines.

  • Launch of a new GME-T4 EVO (turbo 2.0-liter) in 2024.
  • Launch of the new EP6 (1.6-liter I4) in 2025.
  • Introduce production of STLA Large and Frame Battery Trays in 2024.
  • Introduce production of STLA Large Beam Machining in 2025.

Toledo Machining – The 1.2 million square feet facility known for producing steering columns and torque converters will get a $270 million investment.

  • Production of the current 850RE torque converters will continue into 2028.
  • Production of the current 948TE torque converters will continue into 2028.
  • Current Heavy Duty truck steering columns will continue to be produced into 2028.
  • Current production of Jeep JL/JT Super-Module for 4xe models will continue into 2028.
  • Introduce production of STLA Large front cradles.
  • Introduce the production of halfshafts.

Stamping Facilities – 

Sterling Stamping Plant. (Stellantis).

Sterling Stamping – FCA US, LLC’s 2.74 million square foot facility right down the street from Sterling Heights Assembly Plant will receive a $165 million investment. Continue current products to support Detroit Assembly Complex Jefferson, Warren Truck, Toledo, and Sterling Heights Assembly facilities.

Warren Stamping – The 2.1 million square foot facility, will get an investment of $85 million. This will be used to introduce future products to support Detroit Assembly Complex Jefferson, Warren Truck, Toledo, Sterling Heights Assembly, and other North American facilities.

Robert S. Miller

Robert S. Miller is a diehard Mopar enthusiast who lives and breathes all that is Mopar. The Michigander is not only the Editor for MoparInsiders.com, 5thGenRams.com, and HDRams.com but an automotive photographer. He is an avid fan of offshore powerboat racing, which he travels the country to take part in.

Related Articles

Loading new replies...

What is happening in Canada factories?

Reply Like

@Jared B and/or @redriderbob
Under the Warren -> Wagoneer section:

  • Both the Wagoneer/Grand Wagoneer are scheduled for two MCAs, the first in 2025 and the second in 2007

Reply Like

Body code document is floating around the internet if one looks.... Needs updated with Belvedere.... honestly I think they were going to shutter it, Seems that Mid-size truck may have saved it, along with UAW ending at a more reasonable spot.

Reply 1 Like

Here's a crazy thought. What if the Belvedere bound "midsize trucks" (plural), are an American sized version of the Ram 700/ ProMaster Rapid platform mates marketed throughout Latin America. The ProMaster City is gone here, as well as all of its competitors. I doubt all the commercial and fleet customers will want to simply pony up to the full-size Ram ProMaster petrol or electric vans. A lot of commercial and fleet buyers would be interested in a smaller van with the Pacifica's plugin hybrid system as an option.

Reply 2 Likes

@Jared B and/or @redriderbob
Under the Warren -> Wagoneer section:

  • Both the Wagoneer/Grand Wagoneer are scheduled for two MCAs, the first in 2025 and the second in 2007

fixed